Chemical plant common equipment reactor is a comprehensive reaction vessel, operation will be caused by a variety of reasons caused by damage, resulting in production was forced to stop. The following is an introduction to the causes and treatment of reactor seal leakage:
Fault phenomenon: seal leakage
◆Cause of failure:
◎Packing seal
1、Stirring shaft is worn or corroded at the packing, resulting in too large a gap;
2、Improper position of oil ring or blockage of oil circuit can not form oil seal;
3、The gland is not pressed tightly, the quality of packing is poor, or it is used for too long;
4, packing box corrosion.
◎Mechanical seal
1、Deformation of dynamic and static ring end face, bruising;
2, the end of the surface pressure is too large, the friction side of the thermal deformation;
3, sealing ring selection material is not right, not enough compression force, or V-shaped sealing ring installed in reverse, losing sealing;
4, axis and static ring end face vertical error is too large;
5, operating pressure, temperature instability, hard particles into the friction vice;
6, the amount of shaft string exceeds the target;
7、Leakage from the set joints of dynamic and static rings.
◆Handling method:
◎ Packing seal:
1、Replace or repair the mixing shaft and process it on machine tool to ensure the roughness;
2、Adjust the position of oil ring and clean the oil circuit;
3、Press the packing, or replace the packing;
4, repair or replacement;
◎ Mechanical seal:
1, replace the friction vice or regrind;
2, adjust the ratio of pressure to be appropriate, strengthen the cooling system, take away the heat in time;
3, seal selection, installation should be reasonable, there should be enough compression force;
4, stop the machine, re-finding, to ensure that the non-perpendicularity is less than 0.5mm;
5, strict control of process indicators, particles and crystals can not enter the friction vice;
6, adjustment, overhaul to make the shaft runout to standard;
7、Improve the installation process, or the amount of surplus should be appropriate, or the adhesive should be good and firm.
Need to know more about the content of the reactor, please continue to pay attention to us.
E-mail: service@chinareactor.com
Add: Hongshan Town Industrial Park, Chongzheng Road, Zichuan District, Zibo City, Shandong Province